Close Print

Our Recommendation

Make
LIEBHERR
Model
HS 8008 (S/N 188295) (Crawler Crane)
Engine
D
Application
Recommendation
Capacity (ltr)
Engine (D) (MAN D2842 LE)
  (a, b)
35.0
Transmission
From Hydraulics
Coolant
  (c)
80.0
Hydraulics (with multi-disc brakes)
  (d, e, f)
1,300
Grease Points
1
QUAKERTEK TERMOPLEX 220 EP (g, h)
2
QUAKERTEK ALHENA 1 EP
3
QUAKERTEK ALHENA 2 EP
Main Boom Adjustment Winch
VERKOL GT-8/75w90 (i, j, k)
7.5
Power Divider
VERKOL GT-8/75w90 (l, m, n)
13.5
Rope Lug
CORVUS 220 EP
0.4
Slew Gear Transmission (each)
VERKOL GT-8/75w90 (o, p, q)
11.2
Telescopic Boom
 
Travel Gears (each)
VERKOL GT-8/75w90 (r, s, t)
34.0
Tugger Winch
CORVUS 220 EP
3.0
Winches 1 & 2 (35 tonne rope pull each)
VERKOL GT-8/75w90 (u, v, w)
30.0

General Notes

There are no notes to display for this model

Lubricant / Capacity Notes

a.
>-20°C
b.
Alternative recommendations, >-20°C: EO LIB E6 10W-40
c.
Mix ratio, 50% >-35°C
d.
-25°C to 50°C
e.
Alternative recommendations, -50°C to 30°C: HY LIB HyPlus Arctic
f.
Alternative recommendations, -25°C to 50°C: HY LIB HyPlus 46
g.
-20°C to 150°C
h.
Alternative recommendations, -55°C to 140°C: QUAKERTEK ALHENA 1 EP
i.
-50°C to 30°C
j.
Alternative recommendations, >-40°C: CORVUS 220 EP
k.
Alternative recommendations, >-25°C: SALDUBA 80w90 LS / VERKOL GT-7/80w90 EP
l.
-50°C to 30°C
m.
Alternative recommendations, >-40°C: CORVUS 220 EP
n.
Alternative recommendations, >-25°C: SALDUBA 80w90 LS / VERKOL GT-7/80w90 EP
o.
-50°C to 30°C
p.
Alternative recommendations, >-40°C: CORVUS 220 EP
q.
Alternative recommendations, >-25°C: SALDUBA 80w90 LS / VERKOL GT-7/80w90 EP
r.
-50°C to 30°C
s.
Alternative recommendations, >-40°C: CORVUS 220 EP
t.
Alternative recommendations, >-25°C: SALDUBA 80w90 LS / VERKOL GT-7/80w90 EP
u.
-50°C to 30°C
v.
Alternative recommendations, >-40°C: CORVUS 220 EP
w.
Alternative recommendations, >-25°C: SALDUBA 80w90 LS / VERKOL GT-7/80w90 EP

Oil Change Intervals

Engine (D) (MAN D2842 LE)
Months Max
6
Hours Max
500
Coolant
Months Max
48
Hours Max
4000
Hydraulics (with multi-disc brakes)
Months Max
24
Hours Max
2000
Main Boom Adjustment Winch
Months Max
12
Hours Max
1000
Power Divider
Months Max
12
Hours Max
1000
Rope Lug
Months Max
12
Hours Max
1000
Slew Gear Transmission (each)
Months Max
12
Hours Max
1000
Travel Gears (each)
Months Max
12
Hours Max
1000
Tugger Winch
Months Max
12
Hours Max
1000
Winches 1 & 2 (35 tonne rope pull each)
Months Max
12
Hours Max
1000